The workers camp is completed at construction site of Salkhit wind farm. It has 53 gers, dining gers and office. The engineers of Mobicom Companyareworking to installantenna for its network and high speed internet in Salkhit site camp for workers.

Recently, 650T Zoomlioncranehas been transported and unloaded at the site. Additionally, two Siemens 110/35 kV main transformers have arrived in Salkhit substation.

Batching plant has been installed and ready to start the operation. Currently, 11 foundationexcavation of the Wind Turbine Generation (WTG) is ready, 10 WTG hardstands and rebar bending work for 5 WTG foundations are in progress.

Excavator putting the finishing touches on a WTG foundation

Site camp construction complete

200 tonne Terex crane from New Gobi Rentals arrives on site

Unloading the final load of foundation mounting pieces

Concrete batching plant being assembled on site

Clearing and leveling a WTG laydown area

Two 110kV main transformers arrive and are unloaded

Unloading of the 650 ton crane