On October 19th, 2012, Clean Energy hosted media representatives at the Salkhit construction site. The tour was organized by the Millennium Challenge Account-Mongolia and aimed at introducing the projects and programs the MCA has implemented and partnered with in Mongolia.
Many parts of the Tuul River Valley have been heavily deforested. Restoration of the forests will require a sustained professional effort over several years. According to the Presidential Decree dated April 14, 2010 the National Tree Planting Day was announced to take place every second Saturday of May and October respectively each year.
The erection team comprising of 15 members completed the erection over 3 days. A 650 ton crane, which is the only one in Mongolia, is being used for the erection work.
Clean Energy LLC of Newcom Group, building Mongolia’s first large-scale wind farm, regularly conducts community meetings with the residents of the Sergelen soum, where the wind farm is located, aiming to inform the local residents of the progress of the construction of the farm
The workers camp is completed at construction site of Salkhit wind farm. It has 53 gers, dining gers and office. The engineers of Mobicom Companyareworking to installantenna for its network and high speed internet in Salkhit site camp for workers.
Mongolia has begun developing its renewable energy industry which would be considered as the priority of energy sector's development, Mongolian energy minister D.Zorigt said.